Status: Milling and overlay from 112th Pl. to 120th Ave. have been completed, and we’ll be going back in a few weeks to stripe the asphalt. The bore crew moved in on Monday and is getting set up to begin boring early next week. We are boring under the intersection of 112th and Irma to minimize traffic intStatus: Milling and overlay from 112th Pl. to 120th Ave. have been completed, and we’ll be going back in a few weeks to stripe the asphalt. The bore crew moved in on Monday and is getting set up to begin boring early next week. We are boring under the intersection of 112th and Irma to minimize traffic interruptions.


Impacts: Watch for the closure of Irma from E 112th Ave. to E 112th Pl. for tunneling operations. Continue to watch for door hangers notifying you of any work in your area. Sometimes we have minor interruptions to water / sewer services, but notifications will go out at least 48 hours in advance. All of our work and schedules are weather dependent.


Questions? Concerns?: Please let us know if you have any questions or concerns. It’s easy to reach us, all of our contacts are listed below.


We are nearing the finish line!


Shawn August

Project Manager

BT Construction, Inc.erruptions.


Impacts: Watch for the closure of Irma from E 112th Ave. to E 112th Pl. for tunneling operations. Continue to watch for door hangers notifying you of any work in your area. Sometimes we have minor interruptions to water / sewer services, but notifications will go out at least 48 hours in advance. All of our work and schedules are weather dependent.


Questions? Concerns?: Please let us know if you have any questions or concerns. It’s easy to reach us, all of our contacts are listed below.


We are nearing the finish line!



Shawn August

Project Manager

BT Construction, Inc.