September 10, 2021

Status: Milling and overlay have begun and are still on track to be completed from 112th Pl. to 120th Ave. this weekend. There is a stretch from Truda Dr. to Fowler Dr. that we will complete tomorrow to avoid impacting the STEM Lab school at Irma and Phillips.


In order to minimize traffic impacts in the neighborhood, we have pushed the start date of the tunneling to Monday. We are boring under the intersection of 112th and Irma to minimize traffic interruptions, but Irma will need to be closed from E 112th Ave. to E 112th Pl. to accommodate the work.


Impacts: Watch for the closure of Irma from E 112th Ave. to E 112th Pl. for tunneling operations starting on Monday, and rolling lane closures this weekend from 112th Pl. to 120th Ave. for paving. We are down to final details in the neighborhood, but continue to watch for door hangers notifying you of work in your area. There may be minor interruptions to water / sewer services for line relocations, and notifications will go out at least 48 hours in advance. Our work and schedules are weather—and supply chain—dependent.


Reach Out: Please let us know if you have any questions or concerns and we will get back to you right away. All of our contacts are listed below.


Here’s to a well-deserved weekend!



Shawn August

Project Manager

BT Construction, Inc.