Status: A few more rainy days slowed us just a bit, but despite the conditions crews still made great progress. Approximately 140’ of the planned 180’ of 36” steel casing was installed on the trenchless crossing of 120th — boring to the south. The neighborhood team is working their way north on Irma Street and is coming up on 114th Pl. Our third crew worked this week to install 1000’ of pipe, heading north on Race Street from 120th.


Impacts: Door hangers will notify you when work is in your area, so watch for those. We anticipate that work on each block will take approximately 1-2 weeks. There may be some minor interruptions to water / sewer services for service line relocations, however, service interruption notifications will go out at least 48 hours in advance. All work and schedules are weather dependent.


Have any questions or concerns? Please reach out via the contacts below. Have a great weekend!


Shawn August

Project Manager

BT Construction, Inc