March 4, 2022
Status: Crews were back on the job this week after the crazy, cold and snowy weather. We had to deal with some odds and ends to get back on track, and now pressure testing — and then the tie-in at 112th — are scheduled for next week.
Impacts: When the crews work on tying into the bore on the north side of 112th, there will be a short duration closure between 112th Ave and 112th Place, so be on the lookout for that.
Please remember that our work and estimated schedules are always weather dependent.
Question or concern?: Feel free to let us know! Please reach out via one of the contacts listed below and we will get back to you as soon as possible.
Have a great weekend and we will see you out there next week!

Shawn August
Project Manager
BT Construction, Inc.