March 18, 2022

Status: We are happy to announce that the tie-in at 112th was completed on Wednesday. We need some warmer weather to complete the asphalt milling and overlay on Leroy Drive, but in the meantime the streets are back open to traffic.


Impacts: There are no traffic impacts at this time, however there will be some impacts when we perform the asphalt milling and overlay on Leroy Drive. We will keep you posted as we get closer to that work.


Please remember that our work and estimated schedules are always weather dependent.


Happy to Help: Have a question or concern? Just let us know via one of the contacts listed below and we will respond as soon as we can.


Here’s to the weekend—have a great one!



Shawn August

Project Manager

BT Construction, Inc.