June 4, 2021

Status: Another short week, but we didn’t let that stop us! Here’s an update on our crew locations as of today. Pipe installation to Malley Drive is within reach of the neighborhood crew. The boring crew—moving south from 120th—continues work on installing the carrier (PVC) pipe inside the casing. The pipe crew moving north on Race Street from 120th is now approaching the Northglenn Maintenance and Operations Facility. In total we have installed 3900 feet of pipe so far.


Impacts: Approximately 1-2 weeks is our expected length of time for work on each block. As crews get near you, you’ll get a door hanger, so watch for those. Some minor interruptions to water / sewer services for line relocations may occur, however, notifications will go out at least 48 hours in advance. All work and schedules are weather dependent.


Please feel free to reach out to us if you have any questions or concerns — all of our contacts are listed below.


Thanks for your patience during this work, and happy weekend!


Shawn August

Project Manager

BT Construction, Inc