Force Main A Replacement Update

June 11, 2021

Status: Great progress was made this week, and the biggest news is that the trenchless crossing of 120th is now complete! The neighborhood crew reports that pipe has been installed all the way past Malley Drive. The Race Street pipe crew — moving north from 120th — has reached the south side of the Northglenn Maintenance and Operations Facility.


Impacts: Our expected length of time for work on each block is approximately 1-2 weeks. When you receive a door hanger


you’ll know the crews are getting close to your property. There may be some minor interruptions to water / sewer services for line relocations, and notifications will go out at least 48 hours in advance. Please remember that all work and schedules are weather dependent.


Questions? Concerns? It’s easy to reach us — all of our contacts are listed below.


We are moving at a great pace, and your patience and cooperation is very much appreciated.


Here’s to the weekend!


Shawn August

Project Manager

BT Construction, Inc