We are back on the job after a wonderful Fourth of July holiday — we hope yours was great too!


Status: Here’s the latest: As of today the crew on the south end of the neighborhood on Irma Drive has pipe in the ground to Truda Drive. The north side crew has turned the corner from Irma Drive onto 120th and are nearly to Race Street. Despite the short week we made great progress.


Impacts: We estimate that work on each block will take approximately 1-2 weeks. You will receive a door hanger when work is in your area. There may be some minor interruptions to water / sewer services for line relocations—notifications will go out at least 48 hours in advance. Our work and estimated schedules are always weather dependent.


Need to Reach Us? It’s easy! All of our contacts are listed below.


Thanks so much for your patience during this work.