Status: The overall project is now over 50% complete, with 65% of the force main 24” pipe installed! Here’s the latest on where the crews are now: Our neighborhood crew on Irma Drive really made good progress this past week with pipe installed to 120th. The north side crew is at the City of Northglenn Maintenance & Operations Facility and is moving north towards E. 124th Avenue.


Impacts: Watch for door hangers notifying you when work is nearby. Work on each block lasts approximately 1-2 weeks. There may be minor interruptions to water / sewer services for line relocations, and notifications will go out at least 48 hours in advance. Work and schedules are always weather dependent.


Reach Out: It’s easy to reach us if you have any questions or concerns. All of our contacts are listed below.


We really appreciate your patience during this work. Thank you.


Stay cool out there!


Shawn August

Project Manager

BT Construction, Inc.