January 21, 2022

Status: The pipe crew is rounding the corner onto Irma Drive as we speak, despite having to work around some very cold temps this week. The finish line is in sight!


Impacts: You can expect some intermittent lane closures during the pipe installation along Irma Drive. Watch for door hanger notifications— if crews are in your area you will get one. And please remember that there may be some minor interruptions to water / sewer services during this work, but you will receive a notification at least 48 hours in advance if you will be affected.


Our work is always weather dependent.


Question / Concern? Have a question or concern about the project? We can help. Please don’t hesitate to reach out to us. Our contacts are listed below.


We will see you out there next week. Have a great weekend!



Shawn August

Project Manager

BT Construction, Inc.