January 14, 2022

Status: The Leroy Drive pipe installation is nearly complete! The crew will be moving onto Irma Drive early next week to finish up that last portion—and the weather looks like it might cooperate.


Impacts: Continue to watch for intermittent lane closures during the pipe installation along Leroy Drive, and next week along Irma Drive. If crews are in your area you will receive a door hanger notification. Remember that there may be some minor interruptions to water / sewer services as we move along, but you will receive a notification at least 48 hours in advance if you will be affected.


Please remember that our estimated schedules and work are always weather dependent.


Reach Out: Have a question or concern about the project? Please reach out to us. All of our contacts are listed below.


Thanks for your continued patience during this work. Here’s to the weekend!



Shawn August

Project Manager

BT Construction, Inc.