- kortniehurd
February 18, 2022
Status: While we don’t have a lot of exciting news to report this week, good progress was still made on the job. While working around the crazy snowstorms, crews have been buttoning up some important odds and ends. The pressure testing and tie-in at 112th has been moved to next week.
Impacts: Work on tying into the bore on the north side of 112th will require a short duration closure between 112th Ave and 112th Place, so watch for that when traveling in the area.
Our work and estimated schedules always weather dependent.
Have a question or concern? We are here to help. Please reach out via one of the contacts listed below and we will get back to you as soon as possible.
Enjoy the weekend before the cold moves in next week!

Shawn August
Project Manager
BT Construction, Inc.