Status: Not a lot to report this week except to say we are making great progress on pipe installation along Leroy Drive—and that’s all the news we need! The map will show you our current location.


Impacts: There may be intermittent lane closures during the pipe installation along Leroy Dr. Be sure to watch for door hangers notifying you if crews are in your area. There may be minor interruptions to water / sewer services along the way, but notifications will go out at least 48 hours in advance.


The weather is still on our side, but remember that schedules and work are always weather dependent.


Have a question?: We have an answer! Please don’t hesitate to reach out if you have any questions or concerns. All of our contacts are listed below.


We continue to appreciate your patience during this work—have a fantastic weekend!



Shawn August

Project Manager

BT Construction, Inc.