August 20, 2021

Status: We are happy to announce that pipe installation in the neighborhood is ahead of schedule and we anticipate its completion by the end of the month. Crews will circle back to complete the asphalt milling and overlay, but material and trucking shortages have delayed that for now.


In the meantime, we will be running one pipe crew for the remainder of the project. The remainder of the maintenance facility work will be the last part of the project, when we tie into the existing line coming up from the neighborhood.


Impacts: As we button up final details in the neighborhood, watch for door hangers notifying you when work is in your area. There may be minor interruptions to water / sewer services for line relocations, and notifications will go out at least 48 hours in advance. Our work and schedules are always weather—and supply chain—dependent.


Questions? Concerns? Just let us know if you have any questions or concerns. All of our contacts are listed below.


Thanks for your continued patience during this work. Have a great weekend!


Shawn August

Project Manager

BT Construction, Inc.