Status: First of all, thank you for your patience during our weekend work! We were back up and running this week and made good progress. Here’s the latest: Our neighborhood crew on Irma Drive has pipe in the ground to just short of 120th. The north side crew is at the City of Northglenn Maintenance & Operations Facility and is closing in on E. 124th Avenue.
Impacts: Remember to watch for door hangers notifying you when work is in your area. We anticipate that work on each block will last approximately 1-2 weeks. There may be minor interruptions to water / sewer services for line relocations, and notifications will go out at least 48 hours in advance. All work and schedules are always weather dependent.
Reach Out: Please let us know if you have any questions or concerns. All of our contacts are listed below.
Happy weekend!

Shawn August
Project Manager
BT Construction, Inc.