The Project: Lift Station A collects nearly all sewage from Northglenn and pumps it through Force Main A to the Wastewater Treatment Plant in Weld County. The lift station and a portion of its force main are being replaced due to deteriorated condition, which has caused frequent breaks.


Status: Construction will be in full swing next Monday, 4/12, at the north side of the intersection of 112th Avenue and Irma Drive. A second crew will start on Monday, 4/19, on the north side of 112th Avenue and Irma Drive.


Impacts: We expect that work on each block will take approximately 1-2 weeks. Properties affected by the construction will receive notifications before work in the area begins, so watch for door hangers. Water / sewer services may have minor interruptions for service line relocations, and customers will be advised of these service interruptions at least 48 hours ahead of time.


It’s easy to get in touch if you have any questions or concerns. All of our contact venues are listed below.


Thanks everyone,


Shawn August

Project Manager

BT Construction, Inc