April 30, 2021

Status: It was another week of good progress, and now we will have three crews on the job. One crew is heading north on Irma Street between Graves and E 114th Pl. Another is starting on the trenchless crossing of 120th—setting up on the north side of 120th and boring to the south. A third crew is starting next week at 120th and Race, and will be working their way north.


Impacts: Work on each block should take approximately 1-2 weeks. You will be notified before work begins in your area, so watch for door hangers. There may be some minor interruptions to water / sewer services for service line relocations. Service interruption notifications will go out at least 48 hours in advance.


Please reach out if you have any questions or concerns.


Have a great weekend!


Shawn August

Project Manager

BT Construction, Inc


7 views0 comments

Recent Posts

See All

Status: All streets are fully open and the crews are cleaning up and moving out of the area. Now we wait for warmer weather and fully operational asphalt plants to mill and pave. Sod replacement at Ja